Sutton Landfill Site is operational in Ashfield with a recorded capacity of 3 MW, and has been generating since 2000-03-01.
Planning and build timeline
| Application submitted | 1999-10-08 |
| Permission granted | 2000-01-06 3 months after submission |
| Operational | 2000-03-01 2 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crow Trees Farm Solar Photovoltaics · Operational | 4.7 | 2.4 km |
Twin Yards Solar Farm Solar Photovoltaics · Operational | 5 | 2.8 km |
Land At Debdale Lane Solar Photovoltaics · Operational | 5 | 5.8 km |
Meadow Lane Solar Farm Solar Photovoltaics · Under Construction | 19.6 | 6.6 km |
Newstead and Annesley Wind Turbine Wind Onshore · Operational | 1.5 | 7.1 km |
Padleywood Farm Solar Photovoltaics · Operational | 5 | 7.5 km |
Averhill Farm Solar Photovoltaics · Operational | 5 | 7.5 km |
Land North of the Wood at Averill Farm Solar Photovoltaics · Operational | 5 | 8 km |
How big is Sutton Landfill Site?
Sutton Landfill Site has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Sutton Landfill Site?
REPD records the operator as Waste Notts Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Sutton Landfill Site approved and built?
The application was submitted on 1999-10-08. Permission was granted on 2000-01-06, 3 months later. The site became operational on 2000-03-01, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 661.