Renewable sites › Sutton Landfill Site
Sutton Landfill Site
Sutton Landfill Site is an operational 3 MW landfill gas site in Ashfield, generating since 1 March 2000. Planning permission was granted on 6 January 2000, 3 months after submission. Operator of record: Waste Notts Ltd.
Planning and build timeline
| Application submitted | 8 October 1999 |
| Permission granted | 6 January 2000 3 months after submission |
| Operational | 1 March 2000 2 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Ashfield: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Sutton Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 4.7 | 2.4 km |
Solar Photovoltaics · Operational | 5 | 2.8 km |
Solar Photovoltaics · Operational | 5 | 5.8 km |
Solar Photovoltaics · Under Construction | 19.6 | 6.6 km |
Wind Onshore · Operational | 1.5 | 7.1 km |
Solar Photovoltaics · Operational | 5 | 7.5 km |
Solar Photovoltaics · Operational | 5 | 7.5 km |
Solar Photovoltaics · Operational | 5 | 8 km |
How big is Sutton Landfill Site?
Sutton Landfill Site has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Sutton Landfill Site?
REPD records the operator as Waste Notts Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Sutton Landfill Site approved and built?
The application was submitted on 8 October 1999. Permission was granted on 6 January 2000, 3 months later. The site became operational on 1 March 2000, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 661.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode