Renewable sites › Ling Hall 1
Ling Hall 1
Ling Hall 1 is an operational 3 MW landfill gas site in Rugby, generating since 25 August 2000. Planning permission was granted on 28 May 1998, 3 months after submission. Operator of record: Summerleaze.
Planning and build timeline
| Application submitted | 13 February 1998 |
| Permission granted | 28 May 1998 3 months after submission |
| Operational | 25 August 2000 27 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Rugby: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Ling Hall 1’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Rugby
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 7 | 0.7 km |
Battery · Under Construction | — | 1.8 km |
Landfill Gas · Operational | 2.4 | 8.9 km |
EfW Incineration · Operational | 4.5 | 11.3 km |
Solar Photovoltaics · Operational | 18.3 | 11.5 km |
Landfill Gas · Operational | 2.3 | 11.9 km |
Solar Photovoltaics · Under Construction | 0.5 | 12.2 km |
Landfill Gas · Operational | 1 | 12.4 km |
How big is Ling Hall 1?
Ling Hall 1 has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ling Hall 1?
REPD records the operator as Summerleaze. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ling Hall 1 approved and built?
The application was submitted on 13 February 1998. Permission was granted on 28 May 1998, 3 months later. The site became operational on 25 August 2000, 27 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 758.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode