Coventry
Coventry is operational in Coventry with a recorded capacity of 4.5 MW, and has been generating since 2001-09-28.
Planning and build timeline
| Application submitted | 1998-06-15 |
| Permission granted | 1998-11-16 5 months after submission |
| Operational | 2001-09-28 34 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Waverley Wood II Landfill Gas · Operational | 2.4 | 6.5 km |
Coventry National Grid Substation Battery · Operational | 49.9 | 6.7 km |
Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels Solar Photovoltaics · Under Construction | 25 | 7.4 km |
Little Beanit Farm, Balsall Common - Battery Storage Battery · Under Construction | 200 | 9.2 km |
Ling Hall Solar Photovoltaics · Operational | 7 | 10.6 km |
Ling Hall 1 Landfill Gas · Operational | 3 | 11.3 km |
Symmetry Park Energy Centre Battery · Under Construction | — | 13.1 km |
Land South of Pogmore Spinney Solar Photovoltaics · Operational | 5 | 13.5 km |
How big is Coventry?
Coventry has a recorded installed capacity of 4.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Coventry?
REPD records the operator as Coventry & Solihull WDC. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Coventry approved and built?
The application was submitted on 1998-06-15. Permission was granted on 1998-11-16, 5 months later. The site became operational on 2001-09-28, 34 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 895.