Renewable sites › Limekiln Wind Farm
Limekiln Wind Farm
Limekiln Wind Farm is an operational 79.8 MW onshore wind farm in Scotland, generating since 1 April 2025. Planning permission was granted on 21 June 2019, 36 months after submission. Operator of record: Boralex/Infinergy.
Planning and build timeline
| Application submitted | 15 June 2016 |
| Permission granted | 21 June 2019 36 months after submission |
| Operational | 1 April 2025 69 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Limekiln Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 21 | 1.6 km |
Battery · Operational | 5 | 1.6 km |
Battery · Under Construction | 34 | 4.4 km |
Wind Onshore · Operational | 52.5 | 5.8 km |
Wind Onshore · Operational | 2.6 | 8.8 km |
Wind Onshore · Operational | 5.2 | 8.8 km |
Wind Onshore · Operational | 4.9 | 8.8 km |
Wind Onshore · Operational | 1.5 | 8.9 km |
How big is Limekiln Wind Farm?
Limekiln Wind Farm has a recorded installed capacity of 79.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Limekiln Wind Farm?
REPD records the operator as Boralex/Infinergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Limekiln Wind Farm approved and built?
The application was submitted on 15 June 2016. Permission was granted on 21 June 2019, 36 months later. The site became operational on 1 April 2025, 69 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6005.