Renewable sites › Baillie Wind Farm
Baillie Wind Farm
Baillie Wind Farm is operational in Scotland with a recorded capacity of 52.5 MW, and has been generating since 2013-03-29.
Planning and build timeline
| Application submitted | 2004-07-13 |
| Permission granted | 2010-01-12 66 months after submission |
| Operational | 2013-03-29 39 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hill of Lybster (Wind Turbine - Extension) Wind Onshore · Operational | 1.5 | 3.7 km |
Forss Wind Farm (Extension) Wind Onshore · Operational | 5.2 | 3.9 km |
Hill of Lybster Wind Onshore · Operational | 4.9 | 3.9 km |
Forss Wind Farm Wind Onshore · Operational | 2.6 | 3.9 km |
Dounreay, Thurso - Battery Energy Storage Battery · Under Construction | 34 | 4.3 km |
Limekiln Wind Farm (Extension) Wind Onshore · Operational | 21 | 4.9 km |
Limekiln Wind Farm (Extension) - Battery Battery · Operational | 5 | 4.9 km |
Limekiln Wind Farm Wind Onshore · Operational | 79.8 | 5.8 km |
How big is Baillie Wind Farm?
Baillie Wind Farm has a recorded installed capacity of 52.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Baillie Wind Farm?
REPD records the operator as Baillie Windfarm Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Baillie Wind Farm approved and built?
The application was submitted on 2004-07-13. Permission was granted on 2010-01-12, 66 months later. The site became operational on 2013-03-29, 39 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4021.