Renewable sitesHill of Lybster

Hill of Lybster

Hill of Lybster is an operational 4.9 MW onshore wind farm in Highland, generating since 8 February 2003. Planning permission was granted on 22 June 2001, 14 months after submission. Operator of record: Fivestone Ltd (subsidiary of Abbey Produce).

4.9 MW
Capacity
as recorded in REPD
Operational
Status
since 8 February 2003
Wind Onshore
Technology
Fivestone Ltd (subsidiary of Abbey Produce)
Highland
Authority
Scotland

Planning and build timeline

Application submitted28 April 2000
Permission granted22 June 2001
14 months after submission
Operational8 February 2003
20 months after consent

Screening a site of your own?

RedlineUK · £39

Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hill of Lybster’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.60 km
Wind Onshore · Operational
5.20 km
Wind Onshore · Operational
1.50.5 km
Wind Onshore · Operational
52.53.9 km
Battery · Under Construction
345.3 km
Wind Onshore · Operational
218.4 km
Battery · Operational
58.4 km
Wind Onshore · Operational
79.88.8 km

How big is Hill of Lybster?

Hill of Lybster has a recorded installed capacity of 4.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hill of Lybster?

REPD records the operator as Fivestone Ltd (subsidiary of Abbey Produce). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hill of Lybster approved and built?

The application was submitted on 28 April 2000. Permission was granted on 22 June 2001, 14 months later. The site became operational on 8 February 2003, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3309.