Renewable sitesHill Farm

Hill Farm

Hill Farm is operational in Cherwell with a recorded capacity of 5 MW, and has been generating since 2017-03-01.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-01
Solar Photovoltaics
Technology
NESF (formerly Earthworm)
Cherwell
Authority
England

Planning and build timeline

Application submitted2015-03-31
Permission granted2015-10-16
7 months after submission
Operational2017-03-01
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cherwell’s record on solar

Cherwell has decided 36 solar farms and approved 100%, taking a median of 2.4 months. See every solar farm decision in Cherwell

Other built sites within 15 km

SiteMWDistance
Rickfield Farm solar park
Solar Photovoltaics · Operational
17.2 km
Ardley Fields Farm Landfill Site
Landfill Gas · Operational
1.88.8 km
Ardley EfW
EfW Incineration · Operational
2411.4 km
North Of Field Barn
Solar Photovoltaics · Operational
112.3 km
Blenheim Net Zero Estate
Solar Photovoltaics · Under Construction
512.8 km
Land South West Of Apollo Business Park
Solar Photovoltaics · Operational
1.714.3 km
Tesco Superstore Bicester
Solar Photovoltaics · Under Construction
0.614.3 km
New Stone House
Solar Photovoltaics · Operational
12.514.7 km

How big is Hill Farm?

Hill Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hill Farm?

REPD records the operator as NESF (formerly Earthworm). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hill Farm approved and built?

The application was submitted on 2015-03-31. Permission was granted on 2015-10-16, 7 months later. The site became operational on 2017-03-01, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5164.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council