Renewable sitesBlenheim Net Zero Estate

Blenheim Net Zero Estate

Blenheim Net Zero Estate is under construction in West Oxfordshire with a recorded capacity of 5 MW.

5 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Vanburgh Unit Trust
West Oxfordshire
Authority
England

Planning and build timeline

Application submitted2020-08-12
Permission granted2021-01-08
5 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Oxfordshire’s record on solar

West Oxfordshire has decided 21 solar farms and approved 81%, taking a median of 3.2 months. See every solar farm decision in West Oxfordshire

Other built sites within 15 km

SiteMWDistance
Cassington AD (Waste AD)
Anaerobic Digestion · Operational
2.15.7 km
The Flit
Solar Photovoltaics · Operational
10.56.6 km
Eynsham Solar Farm
Solar Photovoltaics · Operational
13.27.6 km
Aurora Solar Farm
Battery · Under Construction
188 km
Aurora Solar Farm
Solar Photovoltaics · Under Construction
328 km
Southill Solar
Solar Photovoltaics · Operational
4.58.1 km
Rowles Farm solar park
Solar Photovoltaics · Operational
139.2 km
Ardley EfW
EfW Incineration · Operational
249.6 km

How big is Blenheim Net Zero Estate?

Blenheim Net Zero Estate has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Blenheim Net Zero Estate?

REPD records the operator as Vanburgh Unit Trust. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Blenheim Net Zero Estate approved and built?

The application was submitted on 2020-08-12. Permission was granted on 2021-01-08, 5 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8069.