Rickfield Farm solar park is operational in Cherwell with a recorded capacity of 1 MW, and has been generating since 2014-11-01.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-11-01
Solar Photovoltaics
Technology
Western Power Distribution
Cherwell
Authority
England

Planning and build timeline

Application submitted2013-08-05
Permission granted2013-11-01
3 months after submission
Operational2014-11-01
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cherwell’s record on solar

Cherwell has decided 36 solar farms and approved 100%, taking a median of 2.4 months. See every solar farm decision in Cherwell

Other built sites within 15 km

SiteMWDistance
North Of Field Barn
Solar Photovoltaics · Operational
15.1 km
Hill Farm
Solar Photovoltaics · Operational
57.2 km
Epwell Grounds Farm solar park
Solar Photovoltaics · Operational
77.9 km
Land South West Of Apollo Business Park
Solar Photovoltaics · Operational
1.78.5 km

How big is Rickfield Farm solar park?

Rickfield Farm solar park has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Rickfield Farm solar park?

REPD records the operator as Western Power Distribution. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Rickfield Farm solar park approved and built?

The application was submitted on 2013-08-05. Permission was granted on 2013-11-01, 3 months later. The site became operational on 2014-11-01, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1240.

Novarly Parcel · official public data, read properly · parcel.novarly.com