Renewable sites › Ardley Fields Farm Landfill Site
Ardley Fields Farm Landfill Site
Ardley Fields Farm Landfill Site is operational in Cherwell with a recorded capacity of 1.8 MW, and has been generating since 1996-12-01.
Planning and build timeline
| Application submitted | 1995-08-16 |
| Permission granted | 1996-01-31 6 months after submission |
| Operational | 1996-12-01 10 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Tesco Superstore Bicester Solar Photovoltaics · Under Construction | 0.6 | 6.7 km |
Ardley EfW EfW Incineration · Operational | 24 | 7.1 km |
Shelswell Park Solar Farm Solar Photovoltaics · Operational | 5 | 7.2 km |
New Stone House Solar Photovoltaics · Operational | 12.5 | 8.6 km |
Hill Farm Solar Photovoltaics · Operational | 5 | 8.8 km |
Home Farm (Merton - solar) Solar Photovoltaics · Operational | 18.3 | 9.8 km |
Rowles Farm solar park Solar Photovoltaics · Operational | 13 | 11.1 km |
Brooks Farm Solar Park Solar Photovoltaics · Operational | 8 | 11.3 km |
How big is Ardley Fields Farm Landfill Site?
Ardley Fields Farm Landfill Site has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ardley Fields Farm Landfill Site?
REPD records the operator as Haul Waste Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ardley Fields Farm Landfill Site approved and built?
The application was submitted on 1995-08-16. Permission was granted on 1996-01-31, 6 months later. The site became operational on 1996-12-01, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 587.
Novarly Parcel · official public data, read properly · parcel.novarly.com