Higher Trevartha Farm

Higher Trevartha Farm is operational in Cornwall with a recorded capacity of 3 MW, and has been generating since 2013-03-31.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-31
Solar Photovoltaics
Technology
Smarter Energy Solutions Ltd
Cornwall
Authority
England

Planning and build timeline

Application submitted2012-08-01
Permission granted2012-08-01
0 months after submission
Operational2013-03-31
8 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on solar

Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Trehawke Barton (Doddycross) Solar Farm
Solar Photovoltaics · Operational
10.63.9 km
Ford Farm Solar Farm
Solar Photovoltaics · Operational
54.7 km
Pensipple Farm
Solar Photovoltaics · Operational
55.2 km
Trequite Farm solar park
Solar Photovoltaics · Operational
9.95.3 km
Wilton Farm (pv)
Solar Photovoltaics · Operational
9.56.6 km
Land At Bake Farm
Solar Photovoltaics · Operational
57.5 km
Newton Ferrers solar park
Solar Photovoltaics · Operational
19.58.3 km
Connon Bridge Landfill
Landfill Gas · Operational
18.8 km

How big is Higher Trevartha Farm?

Higher Trevartha Farm has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Higher Trevartha Farm?

REPD records the operator as Smarter Energy Solutions Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Higher Trevartha Farm approved and built?

The application was submitted on 2012-08-01. Permission was granted on 2012-08-01, 0 months later. The site became operational on 2013-03-31, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1067.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council