Novarly ParcelRenewable sites

Renewable sitesTrequite Farm solar park

Trequite Farm solar park

Trequite Farm solar park is operational in Cornwall with a recorded capacity of 9.9 MW, and has been generating since 2014-03-31.

9.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-31
Solar Photovoltaics
Technology
Elgin Energy EsCo
Cornwall
Authority
England

Planning and build timeline

Application submitted2013-05-24
Permission granted2013-08-22
3 months after submission
Operational2014-03-31
7 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on solar

Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Trehawke Barton (Doddycross) Solar Farm
Solar Photovoltaics · Operational
10.61.4 km
Land At Bake Farm
Solar Photovoltaics · Operational
52.8 km
Wilton Farm (pv)
Solar Photovoltaics · Operational
9.52.9 km
Higher Trevartha Farm
Solar Photovoltaics · Operational
35.3 km
Ford Farm Solar Farm
Solar Photovoltaics · Operational
56 km
Howton Farm
Solar Photovoltaics · Operational
4.46.2 km
Newton Ferrers solar park
Solar Photovoltaics · Operational
19.56.4 km
Pensipple Farm
Solar Photovoltaics · Operational
56.5 km

How big is Trequite Farm solar park?

Trequite Farm solar park has a recorded installed capacity of 9.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Trequite Farm solar park?

REPD records the operator as Elgin Energy EsCo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Trequite Farm solar park approved and built?

The application was submitted on 2013-05-24. Permission was granted on 2013-08-22, 3 months later. The site became operational on 2014-03-31, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2129.

Novarly Parcel · official public data, read properly · parcel.novarly.com