Hardingham Solar Farm

Hardingham Solar Farm is operational in Breckland with a recorded capacity of 14.8 MW, and has been generating since 2014-01-05.

14.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-01-05
Solar Photovoltaics
Technology
Solar Century/ Bluefield Solar
Breckland
Authority
England

Planning and build timeline

Application submitted2012-10-01
Permission granted2012-12-21
3 months after submission
Operational2014-01-05
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Breckland’s record on solar

Breckland has decided 27 solar farms and approved 93%, taking a median of 2.7 months. See every solar farm decision in Breckland

Other built sites within 15 km

SiteMWDistance
Hardingham Solar Farm - extension
Solar Photovoltaics · Operational
5.20.3 km
Colton - Solar photovoltaic farm, Battery storage
Solar Photovoltaics · Under Construction
306.1 km
Colton - Solar photovoltaic farm, Battery storage
Battery · Under Construction
306.1 km
Rookery Business Park
Solar Photovoltaics · Operational
57.9 km
Attleborough Ad Plant Limited - Anaerobic Digestion Facility Expansion
Anaerobic Digestion · Operational
19.6 km
The Old Airfield
Solar Photovoltaics · Operational
510.8 km
Weston Airfield Wind Turbines
Wind Onshore · Operational
3.610.8 km
The Everest System
Battery · Operational
0.110.9 km

How big is Hardingham Solar Farm?

Hardingham Solar Farm has a recorded installed capacity of 14.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hardingham Solar Farm?

REPD records the operator as Solar Century/ Bluefield Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hardingham Solar Farm approved and built?

The application was submitted on 2012-10-01. Permission was granted on 2012-12-21, 3 months later. The site became operational on 2014-01-05, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1223.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council