Hardingham Solar Farm is an operational 14.8 MW solar farm in Breckland, generating since 5 January 2014. Planning permission was granted on 21 December 2012, 3 months after submission. Operator of record: Solar Century/ Bluefield Solar.

14.8 MW
Capacity
as recorded in REPD
Operational
Status
since 5 January 2014
Solar Photovoltaics
Technology
Solar Century/ Bluefield Solar
Breckland
Authority
England

Planning and build timeline

Application submitted1 October 2012
Permission granted21 December 2012
3 months after submission
Operational5 January 2014
12 months after consent

Screening a site of your own?

RedlineUK · £39

Breckland approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hardingham Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Breckland’s record on solar

Breckland has decided 27 solar farms and approved 93%, taking a median of 2.7 months. See every solar farm decision in Breckland

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
5.20.3 km
Solar Photovoltaics · Under Construction
306.1 km
Battery · Under Construction
306.1 km
Solar Photovoltaics · Operational
57.9 km
Anaerobic Digestion · Operational
19.6 km
Solar Photovoltaics · Operational
510.8 km
Wind Onshore · Operational
3.610.8 km
Battery · Operational
0.110.9 km

How big is Hardingham Solar Farm?

Hardingham Solar Farm has a recorded installed capacity of 14.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hardingham Solar Farm?

REPD records the operator as Solar Century/ Bluefield Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hardingham Solar Farm approved and built?

The application was submitted on 1 October 2012. Permission was granted on 21 December 2012, 3 months later. The site became operational on 5 January 2014, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1223.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode