Glen Kinglass

Glen Kinglass is an operational 1 MW hydro scheme in Argyll and Bute, generating since 15 May 2021. Planning permission was granted on 19 December 2018, 5 months after submission. Operator of record: Simec/Green Highland Renewables.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 15 May 2021
Small Hydro
Technology
Simec/Green Highland Renewables
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted1 August 2018
Permission granted19 December 2018
5 months after submission
Operational15 May 2021
29 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Argyll and Bute: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Glen Kinglass’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Under Construction
0.49.6 km
Small Hydro · Under Construction
211 km
Small Hydro · Operational
1.511.1 km
Small Hydro · Operational
211.1 km
Pumped Storage Hydroelectricity · Operational
44011.5 km
Small Hydro · Under Construction
1.414.1 km

How big is Glen Kinglass?

Glen Kinglass has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Glen Kinglass?

REPD records the operator as Simec/Green Highland Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Glen Kinglass approved and built?

The application was submitted on 1 August 2018. Permission was granted on 19 December 2018, 5 months later. The site became operational on 15 May 2021, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6687.