Renewable sites › Glen Noe River
Glen Noe River
Glen Noe River is a 2 MW hydro scheme under construction in Argyll and Bute. Planning permission was granted on 9 September 2016, 9 months after submission. Operator of record: RWE Npower Renewables / Innogy.
Planning and build timeline
| Application submitted | 14 December 2015 |
| Permission granted | 9 September 2016 9 months after submission |
| Operational | not recorded |
Screening a site of your own?
Redline runs the record on your own boundary in Argyll and Bute: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Glen Noe River’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pumped Storage Hydroelectricity · Operational | 440 | 6.3 km |
Small Hydro · Operational | 1 | 11 km |
Wind Onshore · Operational | 7.8 | 11.7 km |
Small Hydro · Under Construction | 0.4 | 13.1 km |
How big is Glen Noe River?
Glen Noe River has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Glen Noe River?
REPD records the operator as RWE Npower Renewables / Innogy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Glen Noe River approved and built?
The application was submitted on 14 December 2015. Permission was granted on 9 September 2016, 9 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5962.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode