Renewable sitesEas a Ghaill

Eas a Ghaill

Eas a Ghaill is an operational 1.5 MW hydro scheme in Argyll and Bute, generating since 1 December 2015. Planning permission was granted on 19 September 2014, 2 months after submission. Operator of record: Gilkes Energy.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2015
Small Hydro
Technology
Gilkes Energy
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted24 July 2014
Permission granted19 September 2014
2 months after submission
Operational1 December 2015
14 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Argyll and Bute: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Eas a Ghaill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
20.2 km
Small Hydro · Under Construction
0.43.2 km
Small Hydro · Operational
111.1 km
Pumped Storage Hydroelectricity · Operational
44011.7 km
Wind Onshore · Operational
1513 km

How big is Eas a Ghaill?

Eas a Ghaill has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Eas a Ghaill?

REPD records the operator as Gilkes Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Eas a Ghaill approved and built?

The application was submitted on 24 July 2014. Permission was granted on 19 September 2014, 2 months later. The site became operational on 1 December 2015, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5947.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode