Elms Farm is operational in Vale of White Horse with a recorded capacity of 29 MW, and has been generating since 2015-03-16.
Planning and build timeline
| Application submitted | 2014-05-28 |
| Permission granted | 2014-08-28 3 months after submission |
| Operational | 2015-03-16 7 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Vale of White Horse’s record on solar
Vale of White Horse has decided 23 solar farms and approved 91%, taking a median of 3 months. See every solar farm decision in Vale of White Horse →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hill Farm Solar Park (VoWH) Solar Photovoltaics · Operational | 14.8 | 3.8 km |
Steventon Solar Park Solar Photovoltaics · Operational | 10 | 4.1 km |
Goose Willow Farm Solar Photovoltaics · Operational | 11.5 | 4.6 km |
Landmead Farm (East Hanney) Solar Photovoltaics · Operational | 46 | 4.7 km |
Goose Willow Farm - extension Solar Photovoltaics · Operational | 7 | 4.7 km |
South Car Park - Solar photovoltaic carport system Solar Photovoltaics · Operational | — | 7.1 km |
Avon Road Car Park - Solar Photovoltaic Carport System Solar Photovoltaics · Operational | 1.62 | 7.3 km |
Sutton Courtenay Landfill Scheme Landfill Gas · Operational | 5.6 | 9.7 km |
How big is Elms Farm?
Elms Farm has a recorded installed capacity of 29 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Elms Farm?
REPD records the operator as Bluefield Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Elms Farm approved and built?
The application was submitted on 2014-05-28. Permission was granted on 2014-08-28, 3 months later. The site became operational on 2015-03-16, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1832.