Steventon Solar Park is operational in Vale of White Horse with a recorded capacity of 10 MW, and has been generating since 2014-06-19.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-06-19
Solar Photovoltaics
Technology
Foresight
Vale of White Horse
Authority
England

Planning and build timeline

Application submitted2012-07-18
Permission granted2012-10-17
3 months after submission
Operational2014-06-19
20 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Vale of White Horse’s record on solar

Vale of White Horse has decided 23 solar farms and approved 91%, taking a median of 3 months. See every solar farm decision in Vale of White Horse

Other built sites within 15 km

SiteMWDistance
Goose Willow Farm
Solar Photovoltaics · Operational
11.50.4 km
Goose Willow Farm - extension
Solar Photovoltaics · Operational
70.9 km
Landmead Farm (East Hanney)
Solar Photovoltaics · Operational
461.4 km
Hill Farm Solar Park (VoWH)
Solar Photovoltaics · Operational
14.82.1 km
Elms Farm
Solar Photovoltaics · Operational
294.1 km
Sutton Courtenay Landfill Scheme
Landfill Gas · Operational
5.66.5 km
Sutton Courtney
Landfill Gas · Operational
67.4 km
South Car Park - Solar photovoltaic carport system
Solar Photovoltaics · Operational
7.7 km

How big is Steventon Solar Park?

Steventon Solar Park has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Steventon Solar Park?

REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Steventon Solar Park approved and built?

The application was submitted on 2012-07-18. Permission was granted on 2012-10-17, 3 months later. The site became operational on 2014-06-19, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1817.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council