Renewable sites › Eden Geothermal Limited - Eden Project Energy Centre
Eden Geothermal Limited - Eden Project Energy Centre
Eden Geothermal Limited - Eden Project Energy Centre is operational in Cornwall, and has been generating since 2023-06-19.
Planning and build timeline
| Application submitted | 2021-11-04 |
| Permission granted | 2022-02-10 3 months after submission |
| Operational | 2023-06-19 16 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Eden Project Geothermal Energy Facility Hot Dry Rocks (HDR) · Under Construction | 7 | 0.5 km |
Trenoweth Solar Farm Solar Photovoltaics · Operational | 2.5 | 2.8 km |
West Carclaze Solar Farm Solar Photovoltaics · Operational | 6.5 | 2.9 km |
Tredinnick Fields Solar Photovoltaics · Operational | 5.8 | 3.8 km |
Bodwen Solar Park Solar Photovoltaics · Operational | 5.5 | 4.8 km |
Goonamarth Farm - Wind Turbine Wind Onshore · Under Construction | 4.3 | 5.9 km |
Rew Farm Solar Farm Solar Photovoltaics · Operational | 6.1 | 6.7 km |
Woodlands Barton Solar Farm Solar Photovoltaics · Operational | 4.9 | 7 km |
How big is Eden Geothermal Limited - Eden Project Energy Centre?
REPD does not record an installed capacity for Eden Geothermal Limited - Eden Project Energy Centre.
Who operates Eden Geothermal Limited - Eden Project Energy Centre?
REPD records the operator as Eden Project Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Eden Geothermal Limited - Eden Project Energy Centre approved and built?
The application was submitted on 2021-11-04. Permission was granted on 2022-02-10, 3 months later. The site became operational on 2023-06-19, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9979.