Renewable planning › Solar › Mid Ulster
Solar planning in Mid Ulster
Mid Ulster has decided 8 solar farms and approved 100% of them, taking a median of 3.8 months to decide. Consented capacity: 6 MW. 1 application still awaiting a decision.
How Mid Ulster compares
Against the 298 UK authorities with 5+ solar decisions, Mid Ulster sits in the 77th percentile for approval rate (7 points above the England average) and the 17th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (10)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Solar PV Panels Installation in Dungannon Astatine Limited · LA09/2024/1528/F · 4.4 mo to decide | 0.25 | Awaiting Construction | 2025-05-01 |
Solar Array Development in Dungannon Irwins Feed Limited · LA09/2024/0586/F · 6.4 mo to decide | 0.3 | Awaiting Construction | 2024-12-09 |
Solar PV Panels Installation in Toome Astatine Limited · LA09/2024/1143/F · 1 mo to decide | — | Awaiting Construction | 2024-10-31 |
PV Panels Development in Tobermore Tobermore Concrete Products Limited · LA09/2024/0707/F · 2.1 mo to decide | — | Awaiting Construction | 2024-08-14 |
PV Panels Development in Tobermore Tobermore Concrete Products Limited · LA09/2024/0706/F · 2.1 mo to decide | — | Awaiting Construction | 2024-08-14 |
Drumard Road, Gulladuff - Solar Panels The Green Yard · LA09/2023/0412/F · 14 mo to decide | — | Awaiting Construction | 2024-06-03 |
Solar PV Array Development in Dungannon Henry Marshall Brown Architectural Partnership · LA09/2023/1111/F · 2 mo to decide | 0.15 | Awaiting Construction | 2023-12-20 |
Drum Road, Cookstown - Solar & Battery Development Numalls Energy Ltd · LA09/2023/0331/F | 1 | Application Submitted | 2023-03-27 |
Altmore Road Gaelectric Developments · LA09/2015/1096/F · 5.6 mo to decide | 4.9 | Abandoned | 2016-05-05 |
Dale Farm Solar Farm DFD · LA09/2015/0885/F · 3.8 mo to decide | 4.9 | Operational | 2016-01-21 |
Does Mid Ulster approve solar farms?
Yes — of the 8 solar farms Mid Ulster has decided, 100% were approved (8 granted, 0 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in Mid Ulster?
The median time from application to decision is 3.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Mid Ulster consented?
6 MW has been consented across 8 approved schemes. A further 1 application awaits a decision.
Other technologies in Mid Ulster
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.