Renewable sites › Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels
Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels
Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels is under construction in Rugby with a recorded capacity of 25 MW.
Planning and build timeline
| Application submitted | 2022-10-17 |
| Permission granted | 2023-08-31 10 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Rugby
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Rugby’s record on solar
Rugby has decided 19 solar farms and approved 95%, taking a median of 1.8 months. See every solar farm decision in Rugby →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Coventry National Grid Substation Battery · Operational | 49.9 | 0.9 km |
Coventry EfW Incineration · Operational | 4.5 | 7.4 km |
Judkins Landfill Site Phase 3 Landfill Gas · Operational | 1.2 | 8.4 km |
Judkins Landfill Scheme Landfill Gas · Operational | 2.7 | 8.4 km |
Land South of Pogmore Spinney Solar Photovoltaics · Operational | 5 | 10.9 km |
Basin Bridge Farm Solar Photovoltaics · Operational | 5 | 11.7 km |
Waverley Wood II Landfill Gas · Operational | 2.4 | 13.3 km |
Ling Hall Solar Photovoltaics · Operational | 7 | 13.4 km |
How big is Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels?
Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels?
REPD records the operator as Novus Renewable Services Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels approved and built?
The application was submitted on 2022-10-17. Permission was granted on 2023-08-31, 10 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12597.