Novarly ParcelRenewable sites

Renewable sitesCoventry National Grid Substation

Coventry National Grid Substation

Coventry National Grid Substation is operational in Coventry with a recorded capacity of 49.9 MW, and has been generating since 2023-12-01.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2023-12-01
Battery
Technology
Pivot Power
Coventry
Authority
England

Planning and build timeline

Application submitted2020-07-02
Permission granted2021-01-22
7 months after submission
Operational2023-12-01
34 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels
Solar Photovoltaics · Under Construction
250.9 km
Coventry
EfW Incineration · Operational
4.56.7 km
Judkins Landfill Site Phase 3
Landfill Gas · Operational
1.28.7 km
Judkins Landfill Scheme
Landfill Gas · Operational
2.78.7 km
Land South of Pogmore Spinney
Solar Photovoltaics · Operational
510.4 km
Basin Bridge Farm
Solar Photovoltaics · Operational
512.3 km
Waverley Wood II
Landfill Gas · Operational
2.412.8 km
Little Beanit Farm, Balsall Common - Battery Storage
Battery · Under Construction
20013.3 km

How big is Coventry National Grid Substation?

Coventry National Grid Substation has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Coventry National Grid Substation?

REPD records the operator as Pivot Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Coventry National Grid Substation approved and built?

The application was submitted on 2020-07-02. Permission was granted on 2021-01-22, 7 months later. The site became operational on 2023-12-01, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7885.