Novarly ParcelRenewable sites

Renewable sitesCoventry National Grid Substation

Coventry National Grid Substation

Coventry National Grid Substation is an operational 49.9 MW battery storage site in Coventry, generating since 1 December 2023. Planning permission was granted on 22 January 2021, 7 months after submission. Operator of record: Pivot Power.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2023
Battery
Technology
Pivot Power
Coventry
Authority
England

Planning and build timeline

Application submitted2 July 2020
Permission granted22 January 2021
7 months after submission
Operational1 December 2023
34 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Coventry: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Coventry National Grid Substation’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
250.9 km
EfW Incineration · Operational
4.56.7 km
Landfill Gas · Operational
1.28.7 km
Landfill Gas · Operational
2.78.7 km
Solar Photovoltaics · Operational
510.4 km
Solar Photovoltaics · Operational
512.3 km
Landfill Gas · Operational
2.412.8 km
Battery · Under Construction
20013.3 km

How big is Coventry National Grid Substation?

Coventry National Grid Substation has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Coventry National Grid Substation?

REPD records the operator as Pivot Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Coventry National Grid Substation approved and built?

The application was submitted on 2 July 2020. Permission was granted on 22 January 2021, 7 months later. The site became operational on 1 December 2023, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7885.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode