Caswell Farm Solar Park is an operational 6.7 MW solar farm in Dorset, generating since 23 March 2016. Planning permission was granted on 13 December 2013, 9 months after submission. Operator of record: Juwi Renewable Energies.

6.7 MW
Capacity
as recorded in REPD
Operational
Status
since 23 March 2016
Solar Photovoltaics
Technology
Juwi Renewable Energies
Dorset
Authority
England

Planning and build timeline

Application submitted8 March 2013
Permission granted13 December 2013
9 months after submission
Operational23 March 2016
27 months after consent

Screening a site of your own?

RedlineUK · £39

Dorset approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Caswell Farm Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Dorset’s record on solar

Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
352.2 km
Solar Photovoltaics · Operational
0.36.7 km
Solar Photovoltaics · Operational
0.227.1 km
Solar Photovoltaics · Operational
57.8 km
Solar Photovoltaics · Operational
97.9 km
Solar Photovoltaics · Operational
59.2 km
Large Hydro · Operational
1011.6 km
Solar Photovoltaics · Operational
511.9 km

How big is Caswell Farm Solar Park?

Caswell Farm Solar Park has a recorded installed capacity of 6.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Caswell Farm Solar Park?

REPD records the operator as Juwi Renewable Energies. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Caswell Farm Solar Park approved and built?

The application was submitted on 8 March 2013. Permission was granted on 13 December 2013, 9 months later. The site became operational on 23 March 2016, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1898.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode