Renewable sites › Clifton Farm
Clifton Farm
Clifton Farm is operational in Dorset with a recorded capacity of 35 MW, and has been generating since 2025-09-01.
Planning and build timeline
| Application submitted | 2020-05-05 |
| Permission granted | 2021-05-20 12 months after submission |
| Operational | 2025-09-01 51 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — Parrett Catchment
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Dorset’s record on solar
Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Caswell Farm Solar Park Solar Photovoltaics · Operational | 6.7 | 2.2 km |
Tesco Queensway Place Solar Photovoltaics · Operational | 0.3 | 4.7 km |
Westland Leisure Complex Solar Photovoltaics · Operational | 0.22 | 5.2 km |
Chilton Cantelo Solar Farm Solar Photovoltaics · Operational | 5 | 9.7 km |
Southern Counties Shooting Ground Phase 2 Solar Photovoltaics · Operational | 5 | 10 km |
Southern Counties Shooting Ground Phase 1 Solar Photovoltaics · Operational | 9 | 10.1 km |
Rampisham North Solar Photovoltaics · Operational | 5 | 11.2 km |
Southfield Farm Solar Park Solar Photovoltaics · Operational | 11.5 | 11.9 km |
How big is Clifton Farm?
Clifton Farm has a recorded installed capacity of 35 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Clifton Farm?
REPD records the operator as Voltalia UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Clifton Farm approved and built?
The application was submitted on 2020-05-05. Permission was granted on 2021-05-20, 12 months later. The site became operational on 2025-09-01, 51 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7929.