Tirgwynt
Tirgwynt is an operational 24.6 MW onshore wind farm in Powys, generating since 15 February 2017. Planning permission was granted on 12 October 2010, 37 months after submission. Operator of record: Foresight.
Planning and build timeline
| Application submitted | 24 September 2007 |
| Permission granted | 12 October 2010 37 months after submission |
| Operational | 15 February 2017 76 months after consent |
Screening a site of your own?
Powys approves 68% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Tirgwynt’s recorded coordinate — swap in your own postcode or coordinates.
Powys’s record on onshore wind
Powys has decided 22 onshore wind schemes and approved 68%, taking a median of 36.8 months. See every onshore wind scheme decision in Powys →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 14.5 | 5 km |
Wind Onshore · Operational | 16.8 | 10.2 km |
Wind Onshore · Operational | 15.6 | 10.2 km |
Wind Onshore · Operational | 16.8 | 11.1 km |
Wind Onshore · Operational | 15.3 | 13.6 km |
Wind Onshore · Operational | 3.4 | 14.1 km |
How big is Tirgwynt?
Tirgwynt has a recorded installed capacity of 24.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tirgwynt?
REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tirgwynt approved and built?
The application was submitted on 24 September 2007. Permission was granted on 12 October 2010, 37 months later. The site became operational on 15 February 2017, 76 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3707.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode