Renewable sitesMynydd Clogau Wind Farm

Mynydd Clogau Wind Farm

Mynydd Clogau Wind Farm is operational in Powys with a recorded capacity of 14.5 MW, and has been generating since 2005-12-01.

14.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2005-12-01
Wind Onshore
Technology
Renewable Energy Systems (RES)
Powys
Authority
Wales

Planning and build timeline

Application submitted1998-09-11
Permission granted2002-05-23
44 months after submission
Operational2005-12-01
42 months after consent

Powys’s record on onshore wind

Powys has decided 22 onshore wind schemes and approved 68%, taking a median of 36.8 months. See every onshore wind scheme decision in Powys

Other built sites within 15 km

SiteMWDistance
Tirgwynt
Wind Onshore · Operational
24.65 km
Carno 'A' Wind Farm
Wind Onshore · Operational
16.811 km
Carno 'A'and 'B' Wind Farm, (Extension)
Wind Onshore · Operational
15.611 km
Carno 'B' Wind Farm
Wind Onshore · Operational
16.812.6 km

How big is Mynydd Clogau Wind Farm?

Mynydd Clogau Wind Farm has a recorded installed capacity of 14.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Mynydd Clogau Wind Farm?

REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Mynydd Clogau Wind Farm approved and built?

The application was submitted on 1998-09-11. Permission was granted on 2002-05-23, 44 months later. The site became operational on 2005-12-01, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4684.