Renewable sitesBroadley Copse

Broadley Copse

Broadley Copse is operational in Chichester with a recorded capacity of 2.2 MW, and has been generating since 2018-03-24.

2.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-03-24
Anaerobic Digestion
Technology
Broadley Energy
Chichester
Authority
England

Planning and build timeline

Application submitted2015-08-18
Permission granted2016-02-29
6 months after submission
Operational2018-03-24
25 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Hunters Race Solar Park
Solar Photovoltaics · Operational
9.34.2 km
Southleigh Landfill
Landfill Gas · Operational
3.57.3 km
Former Westhampnett Landfill
Solar Photovoltaics · Operational
7.58 km
Strettington Solar Farm
Solar Photovoltaics · Operational
58.6 km
Donaldsons Nursery, Marsh Farm - Solar Panels
Solar Photovoltaics · Under Construction
0.199.2 km
Merston Solar Park
Solar Photovoltaics · Operational
1010.3 km
Land at Tangmere Airfield
Solar Photovoltaics · Operational
510.7 km
Oving Solar Farm
Solar Photovoltaics · Operational
510.9 km

How big is Broadley Copse?

Broadley Copse has a recorded installed capacity of 2.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Broadley Copse?

REPD records the operator as Broadley Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Broadley Copse approved and built?

The application was submitted on 2015-08-18. Permission was granted on 2016-02-29, 6 months later. The site became operational on 2018-03-24, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6626.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council