Renewable sitesBombardier Factory

Bombardier Factory

Bombardier Factory is an operational 3.8 MW solar farm in Antrim and Newtownabbey, generating since 27 May 2015. Planning permission was granted on 7 February 2014, 3 months after submission. Operator of record: Bombardier Aerospace.

3.8 MW
Capacity
as recorded in REPD
Operational
Status
since 27 May 2015
Solar Photovoltaics
Technology
Bombardier Aerospace
Antrim and Newtownabbey
Authority
Northern Ireland

Planning and build timeline

Application submitted1 November 2013
Permission granted7 February 2014
3 months after submission
Operational27 May 2015
16 months after consent

Screening a site of your own?

RedlineUK · £39

Antrim and Newtownabbey approves 83% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bombardier Factory’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Antrim and Newtownabbey’s record on solar

Antrim and Newtownabbey has decided 12 solar farms and approved 83%, taking a median of 6.5 months. See every solar farm decision in Antrim and Newtownabbey

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
6.44.8 km
Landfill Gas · Operational
3.25 km
Wind Onshore · Operational
2.35.4 km
Anaerobic Digestion · Operational
1.26.6 km
EfW Incineration · Under Construction
14.96.8 km
Wind Onshore · Operational
13.87.2 km
Anaerobic Digestion · Operational
2.111.3 km
Solar Photovoltaics · Operational
1011.7 km

How big is Bombardier Factory?

Bombardier Factory has a recorded installed capacity of 3.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bombardier Factory?

REPD records the operator as Bombardier Aerospace. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bombardier Factory approved and built?

The application was submitted on 1 November 2013. Permission was granted on 7 February 2014, 3 months later. The site became operational on 27 May 2015, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1350.