Solar planning in West Oxfordshire

West Oxfordshire has decided 21 solar farms and approved 81% of them, taking a median of 3.2 months to decide. Consented capacity: 236 MW. 9 applications still awaiting a decision.

81%
Approved
17 granted · 4 refused
3.2 mo
Median decision
UK 2.3 mo
236 MW
Consented
34 MW refused
3
Appeals
1 allowed on appeal

How West Oxfordshire compares

Against the 298 UK authorities with 5+ solar decisions, West Oxfordshire sits in the 8th percentile for approval rate (12 points below the England average) and the 27th percentile for speed.

Decisions by year

510Approved — 1 (2012)Refused — 1 (2012)212Approved — 1 (2013)113Approved — 1 (2014)Refused — 1 (2014)214Approved — 1 (2015)115Refused — 1 (2016)116Approved — 1 (2020)120Approved — 3 (2021)321Approved — 1 (2022)122Approved — 6 (2023)623Approved — 2 (2025)Refused — 1 (2025)325
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (31)

SchemeMWStatusDecided
Windrush Leisure Centre - Solar Panels
West Oxfordshire District Council · 25/01557/PN56 · 1.8 mo to decide
0.19Awaiting Construction2025-09-09
Akeman Solar Park & Battery Storage
British Solar Renewables · 25/00234/FUL · 5.8 mo to decide
20Application Refused2025-08-28
Quarry Solar Farm & Battery Storage Facility
RWE · 24/01565/FUL · 13 mo to decide
35Awaiting Construction2025-07-28
Aston Road, Aston - Solar Panels & Battery Energy Storage System
Ampyr Solar Europe · 25/01702/FUL
40Application Submitted2025-07-25
Caswell Lane, Brize Norton - Solar Farm & Battery Storage
Ampyr Solar Europe · 24/03278/FUL
30Application Submitted2025-01-30
Akeman Solar Park & Battery Storage
British Solar Renewables · 23/02917/FUL · 3 mo to decide
20Revised2024-02-05
Carterton Leisure Centre, Broadshires Way - Solar Panels
West Oxfordshire District Council · 23/02420/FUL · 2.3 mo to decide
Awaiting Construction2023-11-23
Witney Community Hospital, Welch Way- Solar Panels
Oxford Health NHS Foundation Trust · 23/02479/PN56 · 1.6 mo to decide
0.15Awaiting Construction2023-11-03
Ducklington Mill, Standlake Road - Solar Panels
Philip Dennis Foodservice · 23/01987/PN56 · 1.7 mo to decide
0.69Awaiting Construction2023-09-13
Shilton Road - Solar Park
Ecotricity Generation Limited · 22/02472/FUL · 9.6 mo to decide
8Awaiting Construction2023-06-27
Tar Solar Farm
Bluefield Renewable Developments Limited · 21/03711/FUL · 19.3 mo to decide
49.9Awaiting Construction2023-06-27
Quarry Solar Farm & Battery Storage Facility
RWE · 23/01524/FUL
35Revised2023-06-02
Airsea Packaging, Range Road - Solar Panels
Airsea Packing Group Limited · 23/00979/PN56 · 1.6 mo to decide
0.24Awaiting Construction2023-05-22
Akeman Solar Park & Battery Storage
British Solar Renewables · 21/02473/FUL
20Revised2022-08-10
Ducklington Solar Farm
Novus Renewable Services / Innova Renewables · 21/01236/FUL · 10.7 mo to decide
36Under Construction2022-03-01
Downs Road, Curbridge Business Park - Solar Panels
Stewart Milne Timber Systems Limited · 21/03367/PN56 · 1.7 mo to decide
1Awaiting Construction2021-12-01
Sheehan Recycled Aggregates Plant
Sheehan Haulage & Plant Hire Limited · MW.0119/20 · 10 mo to decide
1Awaiting Construction2021-10-01
Blenheim Net Zero Estate
Vanburgh Unit Trust · 20/01817/FUL · 4.9 mo to decide
5Under Construction2021-01-08
Aurora Solar Farm
Low Carbon UK Solar Investment Company · 19/02516/FUL · 4.6 mo to decide
32Under Construction2020-02-10
Shilton Downs Solar Park
Ecotricity · 15/04003/FUL · 4.3 mo to decide
5Appeal Refused2016-03-23
Southill Solar
Sustainable Charlbury (Community) · 15/01523/FUL · 4.3 mo to decide
4.5Operational2015-09-07
Shilton Downs Solar Park
Ecotricity / Next Generation · 14/02156/FUL · 3.5 mo to decide
10.8Revised2015-03-23
Westerfield Farm
Lightsource Renewable Energy · 13/1534/P/FP · 13.1 mo to decide
12.5Operational2014-12-01
Wootton Balk
Lightsource Renewable Energy · 14/0819/P/FP · 2.1 mo to decide
7.5Application Refused2014-08-08
Southill Solar
Sustainable Charlbury · 14/0217/P/FP · 2.7 mo to decide
5Revised2014-05-07
Eynsham Solar Farm
Belltown Power · 13/1277/P/FP · 2.7 mo to decide
13.2Operational2013-12-04
Westerfield Farm
Lightsource Renewable Energy · 13/1129/P/FP · 2.4 mo to decide
12Revised2013-10-22
Kencot Hill Solar Farm
Foresight Solar Fund Limited · 12/0584/P/FP · 2.1 mo to decide
37Operational2012-06-20
Enstone Solar Park
Lomond Holdings Ltd · 11/1924/P/FP · 1.8 mo to decide
1.1Application Refused2012-02-08
Kencot Hill Solar Farm
Private Developer · 11/0412/P/FP� · 3.4 mo to decide
5Revised2011-06-27
Cornbury Park Estate
Alectron Investments Ltd� · 11/0184/P/FP�
5Application Withdrawn2011-04-20

Does West Oxfordshire approve solar farms?

Yes — of the 21 solar farms West Oxfordshire has decided, 81% were approved (17 granted, 4 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in West Oxfordshire?

The median time from application to decision is 3.2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has West Oxfordshire consented?

236 MW has been consented across 17 approved schemes, with 34 MW refused. A further 9 applications awaits a decision.

Other technologies in West Oxfordshire

Battery storage in West OxfordshireOnshore wind in West Oxfordshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.