Novarly ParcelRenewable sites

Renewable sitesBlaengwen

Blaengwen

Blaengwen is an operational 23 MW onshore wind farm in Carmarthenshire, generating since 30 November 2009. Planning permission was granted on 27 March 2007, 9 months after submission. Operator of record: Statkraft and Catamount Energy Corporation.

23 MW
Capacity
as recorded in REPD
Operational
Status
since 30 November 2009
Wind Onshore
Technology
Statkraft and Catamount Energy Corporation
Carmarthenshire
Authority
Wales

Planning and build timeline

Application submitted6 July 2006
Permission granted27 March 2007
9 months after submission
Operational30 November 2009
32 months after consent

Screening a site of your own?

RedlineUK · £39

Carmarthenshire approves 70% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Blaengwen’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Carmarthenshire’s record on onshore wind

Carmarthenshire has decided 10 onshore wind schemes and approved 70%, taking a median of 11.7 months. See every onshore wind scheme decision in Carmarthenshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
57.48.1 km
Wind Onshore · Operational
3.914.1 km

How big is Blaengwen?

Blaengwen has a recorded installed capacity of 23 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Blaengwen?

REPD records the operator as Statkraft and Catamount Energy Corporation. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Blaengwen approved and built?

The application was submitted on 6 July 2006. Permission was granted on 27 March 2007, 9 months later. The site became operational on 30 November 2009, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4670.

Novarly Parcel · official public data, read properly · parcel.novarly.com