Birch Solar Farm & Battery Storage is operational in Colchester.

Capacity
as recorded in REPD
Operational
Status
no operational date
Battery
Technology
Low Carbon Solar Park 22 Limited
Colchester
Authority
England

Planning and build timeline

Application submitted2022-08-22
Permission granted2023-03-20
7 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Colchester’s record on battery storage

Colchester has decided 5 battery storage schemes and approved 100%, taking a median of 5.6 months. See every battery storage scheme decision in Colchester

Other built sites within 15 km

SiteMWDistance
Birch Solar Farm & Battery Storage
Solar Photovoltaics · Operational
400 km
Land Adjacent Claypits Farm (b) (Birch Estate)
Solar Photovoltaics · Operational
2.31.6 km
Land Adjacent Claypits Farm (a)
Solar Photovoltaics · Operational
51.8 km
Bellhouse South
Landfill Gas · Operational
3.92.1 km
Bellhouse Pit Landfill Scheme
Landfill Gas · Operational
2.72.3 km
Birch Airfield
Solar Photovoltaics · Operational
5.62.6 km
Layer Farm - Solar Farm
Solar Photovoltaics · Operational
493.5 km
Wilkin And Sons, Factory Hill - Solar Farm
Solar Photovoltaics · Operational
6.156.6 km

How big is Birch Solar Farm & Battery Storage?

REPD does not record an installed capacity for Birch Solar Farm & Battery Storage.

Who operates Birch Solar Farm & Battery Storage?

REPD records the operator as Low Carbon Solar Park 22 Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Birch Solar Farm & Battery Storage approved and built?

The application was submitted on 2022-08-22. Permission was granted on 2023-03-20, 7 months later. REPD does not record an operational date.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12102.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council