Beddington EfW
Beddington EfW is operational in Sutton with a recorded capacity of 26 MW, and has been generating since 2019-11-01.
Planning and build timeline
| Application submitted | 2012-07-25 |
| Permission granted | 2013-05-15 10 months after submission |
| Operational | 2019-11-01 78 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
London�s Queen Elizabeth II reservoir Solar Photovoltaics · Operational | 6.3 | 11.3 km |
Dolphin Square - Solar panels Solar Photovoltaics · Under Construction | — | 11.8 km |
Biggin Hill Airport, Main Road - Solar PV Array Solar Photovoltaics · Under Construction | 12 | 13.4 km |
Ham Close - 452 Houses, Flats & Leisure Centre Solar Photovoltaics · Under Construction | 0.43 | 13.4 km |
SELCHP ERF EfW Incineration · Operational | 35 | 13.6 km |
How big is Beddington EfW?
Beddington EfW has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Beddington EfW?
REPD records the operator as Viridor. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Beddington EfW approved and built?
The application was submitted on 2012-07-25. Permission was granted on 2013-05-15, 10 months later. The site became operational on 2019-11-01, 78 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 942.