Renewable sites › Barn Farm
Barn Farm
Barn Farm is operational in Tendring with a recorded capacity of 4.2 MW, and has been generating since 2015-08-14.
Planning and build timeline
| Application submitted | 2014-07-10 |
| Permission granted | 2014-10-20 3 months after submission |
| Operational | 2015-08-14 10 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- National Landscape (AONB) — Suffolk Coast & Heaths
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Tendring’s record on solar
Tendring has decided 18 solar farms and approved 83%, taking a median of 3 months. See every solar farm decision in Tendring →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wix Lodge Solar Photovoltaics · Operational | 18.7 | 3.1 km |
Green Farm Solar Photovoltaics · Operational | 5 | 3.3 km |
Chancery Farm (Ardleigh) Solar Photovoltaics · Operational | 11.9 | 10.3 km |
Blue Gates Farm Wind Onshore · Operational | 1.5 | 12.4 km |
Bluegates Solar Park Solar Photovoltaics · Operational | 10.5 | 12.6 km |
University Of Suffolk Campus North Battery · Operational | — | 12.9 km |
Stratton Hall Solar Park Solar Photovoltaics · Operational | 11.6 | 12.9 km |
Chisbon Solar Farm (Frowick Lane) Solar Photovoltaics · Operational | 13 | 13.5 km |
How big is Barn Farm?
Barn Farm has a recorded installed capacity of 4.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Barn Farm?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Barn Farm approved and built?
The application was submitted on 2014-07-10. Permission was granted on 2014-10-20, 3 months later. The site became operational on 2015-08-14, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1959.