Solar planning in Tendring

Tendring has decided 18 solar farms and approved 83% of them, taking a median of 3 months to decide. Consented capacity: 159 MW. 4 applications still awaiting a decision.

83%
Approved
15 granted · 3 refused
3 mo
Median decision
UK 2.3 mo
159 MW
Consented
52 MW refused
1
Appeals
0 allowed on appeal

How Tendring compares

Against the 298 UK authorities with 5+ solar decisions, Tendring sits in the 12th percentile for approval rate (10 points below the England average) and the 32nd percentile for speed.

Decisions by year

35Approved — 2 (2013)213Approved — 1 (2014)Refused — 2 (2014)314Approved — 2 (2015)215Approved — 1 (2021)121Approved — 1 (2022)Refused — 1 (2022)222Approved — 2 (2023)223Approved — 1 (2024)124Approved — 4 (2025)425
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (23)

SchemeMWStatusDecided
Martells Quarry, Slough Lane - Solar Array
Sewells Reservoir Construction Ltd · 25/01368/FUL · 3.2 mo to decide
1Awaiting Construction2025-12-17
Clay Lane, St Osyth - Solar Farm
Lighthouse Development Consulting Limited · 25/00939/FUL · 5.2 mo to decide
20Awaiting Construction2025-11-27
Manheim Colchester Auctions, Colchester Road - Solar PV array
SNRG · 25/01224/NDPNOT · 1.7 mo to decide
0.24Awaiting Construction2025-10-10
Land North of Horsley Cross - Solar Farm & Battery Energy Storage
Mespil Solar Energy · 25/01056/FUL
34Application Submitted2025-07-29
Treestacks Farm, Oakley Road - Solar Panels
HAB Poultry Limited · 25/00446/LUPROP · 1.8 mo to decide
Awaiting Construction2025-06-03
Penguin Random House Distribution, Colchester Road - Solar Panels
Vital Energi · 23/01745/NDPNOT · 1.3 mo to decide
0.91Awaiting Construction2024-01-18
Orchards Holiday Village, Colne Way - Solar Panels
Bourne Leisure Limited · 23/00341/NDPNOT · 2 mo to decide
0.23Awaiting Construction2023-05-02
Thorpe Park Solar Farm, Thorpe Le Soken - Solar Farm
Low Carbon UK Solar Investment Co Limited · 22/02117/FUL · 2 mo to decide
40Awaiting Construction2023-02-17
Halstead Road Eco Hub - Solar Farm & Battery Storage
Naturalis Energy Developments Limited · 21/02181/FUL · 10.5 mo to decide
26Application Refused2022-11-28
Hartley Wood Farm - Solar Farm
Bluefield Renewable Developments Limited/Anglo Renewables · 22/00518/FUL · 5.1 mo to decide
22.5Awaiting Construction2022-08-25
Thorpe Park Solar Farm
Low Carbon UK Solar Investment Co Limited · 21/01860/FUL · 9.1 mo to decide
30Revised2022-08-01
Primrose Hall Solar Farm
Low Carbon Limited · 20/01384/FUL · 5.5 mo to decide
20Awaiting Construction2021-03-19
Jaywick Water Recycling Centre
Anglian Water · 17/02045/CMTR
0.9Operational2017-11-24
Chancery Farm (Ardleigh)
BlackRock · 14/00408/FUL · 20.2 mo to decide
11.9Operational2015-12-22
Green Farm
Hive Energy · 15/00147/FUL · 3 mo to decide
5Operational2015-05-06
Barn Farm
Lightsource Renewable Energy · 14/00918/FUL · 3.4 mo to decide
4.2Operational2014-10-20
Burnt Ash Farm
Kinetica Solar · 13/01340/FUL · 7.5 mo to decide
13.5Appeal Refused2014-08-01
Holland Road
Push Energy · 13/01292/FUL · 3 mo to decide
12Application Refused2014-02-12
Green Farm (Wix Manningtree)
Hive Energy · 13/01210/FUL · 3 mo to decide
7Revised2014-02-07
Barn Farm (Bradfield)
Lightsource Renewable Energy · 13/00958/FUL
3.8Revised2013-11-29
Wix Lodge
Sunsave 25 (Wix Lodge Farm) Limited/ Vogt Solar · 13/00896/FUL · 2.9 mo to decide
18.7Operational2013-11-15
Sladburys Farm
Push Energy · 13/00775/FUL
12Application Withdrawn2013-09-23
Chisbon Solar Farm (Frowick Lane)
ESCO NRG · 13/00360/FUL · 2.6 mo to decide
13Operational2013-07-26

Does Tendring approve solar farms?

Yes — of the 18 solar farms Tendring has decided, 83% were approved (15 granted, 3 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Tendring?

The median time from application to decision is 3 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Tendring consented?

159 MW has been consented across 15 approved schemes, with 52 MW refused. A further 4 applications awaits a decision.

Other technologies in Tendring

Battery storage in TendringOnshore wind in Tendring

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.