Renewable sites › Bakers Farm (solar)
Bakers Farm (solar)
Bakers Farm (solar) is operational in Chichester with a recorded capacity of 12 MW, and has been generating since 2015-03-20.
Planning and build timeline
| Application submitted | 2014-03-19 |
| Permission granted | 2014-10-06 7 months after submission |
| Operational | 2015-03-20 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Chichester’s record on solar
Chichester has decided 24 solar farms and approved 88%, taking a median of 2.6 months. See every solar farm decision in Chichester →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land At Ferry Farm Solar Photovoltaics · Operational | 10 | 1 km |
Sefter Farm AD Plant (Farm AD) Anaerobic Digestion · Operational | 1 | 4.8 km |
Donaldsons Nursery, Marsh Farm - Solar Panels Solar Photovoltaics · Under Construction | 0.19 | 7.1 km |
Park Farm Solar Photovoltaics · Operational | 5 | 7.1 km |
Merston Solar Park Solar Photovoltaics · Operational | 10 | 7.4 km |
Tesco Superstore Shripney Road Solar Photovoltaics · Operational | 0.2 | 9.4 km |
Manor Farm - Shripney Solar Photovoltaics · Operational | 5 | 9.6 km |
Former Westhampnett Landfill Solar Photovoltaics · Operational | 7.5 | 9.9 km |
How big is Bakers Farm (solar)?
Bakers Farm (solar) has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bakers Farm (solar)?
REPD records the operator as Quercus Renewable Holding 2. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bakers Farm (solar) approved and built?
The application was submitted on 2014-03-19. Permission was granted on 2014-10-06, 7 months later. The site became operational on 2015-03-20, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1957.