Renewable sites › Armistead Wind Farm
Armistead Wind Farm
Armistead Wind Farm is operational in Westmorland and Furness with a recorded capacity of 12 MW, and has been generating since 2013-02-11.
Planning and build timeline
| Application submitted | 2008-03-25 |
| Permission granted | 2010-07-15 28 months after submission |
| Operational | 2013-02-11 31 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 5 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Westmorland and Furness’s record on onshore wind
Westmorland and Furness has decided 17 onshore wind schemes and approved 35%, taking a median of 16.8 months. See every onshore wind scheme decision in Westmorland and Furness →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Greaves Solar Farm Solar Photovoltaics · Operational | 5 | 3.2 km |
Lambrigg Wind Farm Wind Onshore · Operational | 6.5 | 6.7 km |
Murley Moss - Additional Solar Design And Build Solar Photovoltaics · Under Construction | — | 7.4 km |
South Stilling Tanks Solar Farm Solar Photovoltaics · Operational | 0.5 | 11.5 km |
Burneside Mill, Burneside Solar Photovoltaics · Operational | 1 | 12 km |
Burneside Mill Solar Array - Phase 3 Solar Photovoltaics · Operational | 0.3 | 12 km |
Burneside Mill Solar Photovoltaics · Operational | 0.5 | 12 km |
How big is Armistead Wind Farm?
Armistead Wind Farm has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Armistead Wind Farm?
REPD records the operator as Banks Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Armistead Wind Farm approved and built?
The application was submitted on 2008-03-25. Permission was granted on 2010-07-15, 28 months later. The site became operational on 2013-02-11, 31 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3986.