Ardrossan is operational in North Ayrshire with a recorded capacity of 24 MW, and has been generating since 2003-12-19.

24 MW
Capacity
as recorded in REPD
Operational
Status
since 2003-12-19
Wind Onshore
Technology
Airtricity
North Ayrshire
Authority
Scotland

Planning and build timeline

Application submitted2002-05-24
Permission granted2003-01-13
8 months after submission
Operational2003-12-19
11 months after consent

North Ayrshire’s record on onshore wind

North Ayrshire has decided 18 onshore wind schemes and approved 78%, taking a median of 8.5 months. See every onshore wind scheme decision in North Ayrshire

Other built sites within 15 km

SiteMWDistance
Ardrossan Extension
Wind Onshore · Operational
60 km
Sorbie Farm
Wind Onshore · Under Construction
92.4 km
Site To North East Of, Lochcraigs Farm
Solar Photovoltaics · Operational
54.2 km
Wardlaw Wood
Wind Onshore · Operational
188.8 km
Nethermains - Solar Farm
Solar Photovoltaics · Under Construction
7.59 km
Millour Hill Community Windfarm
Wind Onshore · Operational
189.9 km
Barkip Anaerobic Digestor (Waste AD)
Anaerobic Digestion · Operational
2.29.9 km
Barkip Landfill Site
Landfill Gas · Operational
1.29.9 km

How big is Ardrossan?

Ardrossan has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ardrossan?

REPD records the operator as Airtricity. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ardrossan approved and built?

The application was submitted on 2002-05-24. Permission was granted on 2003-01-13, 8 months later. The site became operational on 2003-12-19, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3117.