Renewable sites › Westmill Wind Farm
Westmill Wind Farm
Westmill Wind Farm is operational in Vale of White Horse with a recorded capacity of 6.5 MW, and has been generating since 2008-01-01.
Planning and build timeline
| Application submitted | 2000-09-01 |
| Permission granted | 2005-07-07 58 months after submission |
| Operational | 2008-01-01 30 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Westmill Farm - PV Solar Photovoltaics · Operational | 5 | 1.6 km |
Roves Farm (Solar) Solar Photovoltaics · Operational | 12.7 | 3 km |
Sevor Farm Solar Photovoltaics · Operational | 9.3 | 4.3 km |
Corner Copse Solar Farm Battery · Under Construction | — | 5 km |
Corner Copse Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 5 km |
Land at Beech Farm Solar Photovoltaics · Operational | 4.6 | 5 km |
B&Q Swindon DC Solar Photovoltaics · Operational | 2.5 | 5.6 km |
B and Q Distribution Centre Highworth Road Battery · Operational | — | 5.6 km |
How big is Westmill Wind Farm?
Westmill Wind Farm has a recorded installed capacity of 6.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Westmill Wind Farm?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Westmill Wind Farm approved and built?
The application was submitted on 2000-09-01. Permission was granted on 2005-07-07, 58 months later. The site became operational on 2008-01-01, 30 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3264.