Renewable sites › B&Q Swindon DC
B&Q Swindon DC
B&Q Swindon DC is an operational 2.5 MW solar farm in Swindon, generating since 30 January 2016. Planning permission was granted on 26 October 2015, 1 months after submission. Operator of record: Kingfisher Scottish Limited Partnership.
Planning and build timeline
| Application submitted | 16 September 2015 |
| Permission granted | 26 October 2015 1 months after submission |
| Operational | 30 January 2016 3 months after consent |
Screening a site of your own?
Swindon approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with B&Q Swindon DC’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Swindon’s record on solar
Swindon has decided 35 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Swindon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | — | 0 km |
Solar Photovoltaics · Operational | 4.6 | 0.8 km |
Battery · Under Construction | — | 1.7 km |
Solar Photovoltaics · Under Construction | 49.9 | 1.7 km |
Solar Photovoltaics · Operational | 9.3 | 2 km |
Solar Photovoltaics · Operational | 5 | 2.2 km |
Solar Photovoltaics · Under Construction | 0.91 | 2.2 km |
Solar Photovoltaics · Operational | 12.7 | 3.1 km |
How big is B&Q Swindon DC?
B&Q Swindon DC has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates B&Q Swindon DC?
REPD records the operator as Kingfisher Scottish Limited Partnership. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was B&Q Swindon DC approved and built?
The application was submitted on 16 September 2015. Permission was granted on 26 October 2015, 1 months later. The site became operational on 30 January 2016, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5653.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode