Renewable sitesWalney 3

Walney 3

Walney 3 is operational in DECC (S36) with a recorded capacity of 659 MW, and has been generating since 2018-09-13.

659 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-09-13
Wind Offshore
Technology
Orsted (formerly Dong Energy)
DECC (S36)
Authority
England

Planning and build timeline

Application submitted2013-07-30
Permission granted2014-11-07
15 months after submission
Operational2018-09-13
46 months after consent

Other built sites within 15 km

SiteMWDistance
Walney�2
Wind Offshore · Operational
183.68.6 km

How big is Walney 3?

Walney 3 has a recorded installed capacity of 659 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Walney 3?

REPD records the operator as Orsted (formerly Dong Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Walney 3 approved and built?

The application was submitted on 2013-07-30. Permission was granted on 2014-11-07, 15 months later. The site became operational on 2018-09-13, 46 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2533.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council