Averhill Farm is operational in North East Derbyshire with a recorded capacity of 5 MW, and has been generating since 2015-12-16.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-16
Solar Photovoltaics
Technology
Lightsource Renewable Energy
North East Derbyshire
Authority
England

Planning and build timeline

Application submitted2015-04-28
Permission granted2015-09-29
5 months after submission
Operational2015-12-16
3 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North East Derbyshire’s record on solar

North East Derbyshire has decided 19 solar farms and approved 95%, taking a median of 3.5 months. See every solar farm decision in North East Derbyshire

Other built sites within 15 km

SiteMWDistance
Padleywood Farm
Solar Photovoltaics · Operational
50 km
Land North of the Wood at Averill Farm
Solar Photovoltaics · Operational
50.6 km
Meadow Lane Solar Farm
Solar Photovoltaics · Under Construction
19.64.6 km
Twin Yards Solar Farm
Solar Photovoltaics · Operational
55.5 km
Land north of Temple Normanton
Solar Photovoltaics · Operational
4.96.6 km
Crow Trees Farm
Solar Photovoltaics · Operational
4.77.4 km
Glapwell Power
Landfill Gas · Operational
27.4 km
Sutton Landfill Site
Landfill Gas · Operational
37.5 km

How big is Averhill Farm?

Averhill Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Averhill Farm?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Averhill Farm approved and built?

The application was submitted on 2015-04-28. Permission was granted on 2015-09-29, 5 months later. The site became operational on 2015-12-16, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5287.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council