Redhill 2
Redhill 2 is an operational 3 MW landfill gas site in Tandridge, generating since 10 December 2001. Planning permission was granted on 1 November 1999, 3 months after submission. Operator of record: Biffa.
Planning and build timeline
| Application submitted | 22 July 1999 |
| Permission granted | 1 November 1999 3 months after submission |
| Operational | 10 December 2001 25 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Tandridge: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Redhill 2’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Green Belt — Tandridge
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 1.8 | 0.9 km |
Battery · Under Construction | — | 7.2 km |
Solar Photovoltaics · Operational | 1.1 | 14.2 km |
Solar Photovoltaics · Operational | 0.19 | 14.5 km |
Battery · Operational | 6 | 14.6 km |
How big is Redhill 2?
Redhill 2 has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Redhill 2?
REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Redhill 2 approved and built?
The application was submitted on 22 July 1999. Permission was granted on 1 November 1999, 3 months later. The site became operational on 10 December 2001, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 720.