Ray Wind Farm is operational in Northumberland with a recorded capacity of 54.4 MW, and has been generating since 2017-02-05.

54.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-02-05
Wind Onshore
Technology
Vattenfall
Northumberland
Authority
England

Planning and build timeline

Application submitted2005-12-12
Permission granted2010-11-11
59 months after submission
Operational2017-02-05
75 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 5 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Northumberland’s record on onshore wind

Northumberland has decided 31 onshore wind schemes and approved 52%, taking a median of 16.3 months. See every onshore wind scheme decision in Northumberland

Other built sites within 15 km

SiteMWDistance
Ray Battery Storage Facility
Battery · Operational
201.9 km
Green Rigg
Wind Onshore · Operational
366.6 km
Kirkheaton Wind Farm
Wind Onshore · Operational
1.811.9 km

How big is Ray Wind Farm?

Ray Wind Farm has a recorded installed capacity of 54.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ray Wind Farm?

REPD records the operator as Vattenfall. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ray Wind Farm approved and built?

The application was submitted on 2005-12-12. Permission was granted on 2010-11-11, 59 months later. The site became operational on 2017-02-05, 75 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4026.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council