Renewable sites › Pleasance Road - Battery Energy Facility
Pleasance Road - Battery Energy Facility
Pleasance Road - Battery Energy Facility is an operational 49.9 MW battery storage site in Perth and Kinross, generating since 1 June 2023. Planning permission was granted on 1 June 2022, 3 months after submission. Operator of record: Gresham House.
Planning and build timeline
| Application submitted | 25 February 2022 |
| Permission granted | 1 June 2022 3 months after submission |
| Operational | 1 June 2023 12 months after consent |
Screening a site of your own?
Perth and Kinross approves 88% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Pleasance Road - Battery Energy Facility’s recorded coordinate — swap in your own postcode or coordinates.
Perth and Kinross’s record on battery storage
Perth and Kinross has decided 16 battery storage schemes and approved 88%, taking a median of 4.4 months. See every battery storage scheme decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 36.8 | 9.3 km |
Wind Onshore · Operational | 9.2 | 10.6 km |
Wind Onshore · Operational | 14.4 | 12.8 km |
Wind Onshore · Operational | 6.4 | 14.2 km |
How big is Pleasance Road - Battery Energy Facility?
Pleasance Road - Battery Energy Facility has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pleasance Road - Battery Energy Facility?
REPD records the operator as Gresham House. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pleasance Road - Battery Energy Facility approved and built?
The application was submitted on 25 February 2022. Permission was granted on 1 June 2022, 3 months later. The site became operational on 1 June 2023, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9997.