Tullymurdoch Wind Farm

Tullymurdoch Wind Farm is an operational 14.4 MW onshore wind farm in Perth and Kinross, generating since 23 January 2018. Planning permission was granted on 3 September 2014, 25 months after submission. Operator of record: Temporis Capital.

14.4 MW
Capacity
as recorded in REPD
Operational
Status
since 23 January 2018
Wind Onshore
Technology
Temporis Capital
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted13 August 2012
Permission granted3 September 2014
25 months after submission
Operational23 January 2018
41 months after consent

Screening a site of your own?

RedlineUK · £39

Perth and Kinross approves 48% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Tullymurdoch Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Perth and Kinross’s record on onshore wind

Perth and Kinross has decided 27 onshore wind schemes and approved 48%, taking a median of 15.2 months. See every onshore wind scheme decision in Perth and Kinross

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
9.22.9 km
Wind Onshore · Operational
36.86.2 km
Battery · Operational
49.912.8 km

How big is Tullymurdoch Wind Farm?

Tullymurdoch Wind Farm has a recorded installed capacity of 14.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tullymurdoch Wind Farm?

REPD records the operator as Temporis Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tullymurdoch Wind Farm approved and built?

The application was submitted on 13 August 2012. Permission was granted on 3 September 2014, 25 months later. The site became operational on 23 January 2018, 41 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4599.