Renewable sites › Welton Of Creuchies
Welton Of Creuchies
Welton Of Creuchies is an operational 9.2 MW onshore wind farm in Perth and Kinross, generating since 23 January 2018. Planning permission was granted on 6 July 2012, 26 months after submission. Operator of record: Green Cat Renewables.
Planning and build timeline
| Application submitted | 17 May 2010 |
| Permission granted | 6 July 2012 26 months after submission |
| Operational | 23 January 2018 67 months after consent |
Screening a site of your own?
Perth and Kinross approves 48% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Welton Of Creuchies’s recorded coordinate — swap in your own postcode or coordinates.
Perth and Kinross’s record on onshore wind
Perth and Kinross has decided 27 onshore wind schemes and approved 48%, taking a median of 15.2 months. See every onshore wind scheme decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 14.4 | 2.9 km |
Wind Onshore · Operational | 36.8 | 3.3 km |
Battery · Operational | 49.9 | 10.6 km |
How big is Welton Of Creuchies?
Welton Of Creuchies has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Welton Of Creuchies?
REPD records the operator as Green Cat Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Welton Of Creuchies approved and built?
The application was submitted on 17 May 2010. Permission was granted on 6 July 2012, 26 months later. The site became operational on 23 January 2018, 67 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3396.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode