Pentylands Farm

Pentylands Farm is an operational 19 MW solar farm in Swindon, generating since 31 March 2014. Planning permission was granted on 15 November 2012, 3 months after submission. Operator of record: Moser Baer.

19 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2014
Solar Photovoltaics
Technology
Moser Baer
Swindon
Authority
England

Planning and build timeline

Application submitted8 August 2012
Permission granted15 November 2012
3 months after submission
Operational31 March 2014
16 months after consent

Screening a site of your own?

RedlineUK · £39

Swindon approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pentylands Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Swindon’s record on solar

Swindon has decided 35 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Swindon

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
272.3 km
Solar Photovoltaics · Operational
54.1 km
Solar Photovoltaics · Operational
17.84.2 km
Solar Photovoltaics · Under Construction
49.94.3 km
Battery · Under Construction
4.3 km
Solar Photovoltaics · Operational
4.65.3 km
Solar Photovoltaics · Operational
2.56 km
Battery · Operational
6 km

How big is Pentylands Farm?

Pentylands Farm has a recorded installed capacity of 19 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pentylands Farm?

REPD records the operator as Moser Baer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pentylands Farm approved and built?

The application was submitted on 8 August 2012. Permission was granted on 15 November 2012, 3 months later. The site became operational on 31 March 2014, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1593.