Renewable sites › Lynt Farm
Lynt Farm
Lynt Farm is an operational 27 MW solar farm in Swindon, generating since 31 March 2015. Planning permission was granted on 9 January 2015, 7 months after submission. Operator of record: Meag.
Planning and build timeline
| Application submitted | 20 June 2014 |
| Permission granted | 9 January 2015 7 months after submission |
| Operational | 31 March 2015 3 months after consent |
Screening a site of your own?
Swindon approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Lynt Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Swindon’s record on solar
Swindon has decided 35 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Swindon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 19 | 2.3 km |
Wind Onshore · Operational | 6.5 | 5.7 km |
Solar Photovoltaics · Under Construction | 49.9 | 5.9 km |
Battery · Under Construction | — | 5.9 km |
Solar Photovoltaics · Operational | 5 | 6.1 km |
Solar Photovoltaics · Operational | 5 | 6.2 km |
Solar Photovoltaics · Operational | 17.8 | 6.4 km |
Solar Photovoltaics · Operational | 4.6 | 6.8 km |
How big is Lynt Farm?
Lynt Farm has a recorded installed capacity of 27 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lynt Farm?
REPD records the operator as Meag. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lynt Farm approved and built?
The application was submitted on 20 June 2014. Permission was granted on 9 January 2015, 7 months later. The site became operational on 31 March 2015, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2035.