Orton Park Farm

Orton Park Farm is operational in Cumberland with a recorded capacity of 1.6 MW, and has been generating since 2017-06-15.

1.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-06-15
Wind Onshore
Technology
Orton Park Wind Energy
Cumberland
Authority
England

Planning and build timeline

Application submitted2013-04-25
Permission granted2013-07-19
3 months after submission
Operational2017-06-15
47 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cumberland’s record on onshore wind

Cumberland has decided 38 onshore wind schemes and approved 66%, taking a median of 10.3 months. See every onshore wind scheme decision in Cumberland

Other built sites within 15 km

SiteMWDistance
Land between Orton Park Farm
Solar Photovoltaics · Operational
6.41.4 km
Great Orton Wind Farm (Extension)
Wind Onshore · Operational
2.34.2 km
Great Orton
Wind Onshore · Operational
44.5 km
Land west of Welton Road
Solar Photovoltaics · Operational
4.46.7 km
Kingmoor Park
Solar Photovoltaics · Operational
57.2 km
Land at Wreay
Solar Photovoltaics · Operational
58.9 km
High Pow Farm
Wind Onshore · Operational
3.914.8 km

How big is Orton Park Farm?

Orton Park Farm has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Orton Park Farm?

REPD records the operator as Orton Park Wind Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Orton Park Farm approved and built?

The application was submitted on 2013-04-25. Permission was granted on 2013-07-19, 3 months later. The site became operational on 2017-06-15, 47 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3359.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council