Land at Wreay
Land at Wreay is operational in Westmorland and Furness with a recorded capacity of 5 MW, and has been generating since 2017-03-29.
Planning and build timeline
| Application submitted | 2015-07-31 |
| Permission granted | 2016-08-04 12 months after submission |
| Operational | 2017-03-29 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Westmorland and Furness’s record on solar
Westmorland and Furness has decided 39 solar farms and approved 85%, taking a median of 3.8 months. See every solar farm decision in Westmorland and Furness →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land west of Welton Road Solar Photovoltaics · Operational | 4.4 | 6.9 km |
Land between Orton Park Farm Solar Photovoltaics · Operational | 6.4 | 8.5 km |
Orton Park Farm Wind Onshore · Operational | 1.6 | 8.9 km |
Great Orton Wind Farm (Extension) Wind Onshore · Operational | 2.3 | 12.6 km |
Great Orton Wind Onshore · Operational | 4 | 12.9 km |
Kingmoor Park Solar Photovoltaics · Operational | 5 | 13.2 km |
Bells Of Lazonby, Edenholme Bakery - Solar Panels Solar Photovoltaics · Operational | 0.63 | 14.6 km |
How big is Land at Wreay?
Land at Wreay has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Wreay?
REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Wreay approved and built?
The application was submitted on 2015-07-31. Permission was granted on 2016-08-04, 12 months later. The site became operational on 2017-03-29, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5525.